The Short Answer
A new launch is a build period, so a late handover is a real possibility to plan for. The contract usually pays you compensation for lateness, and there is a tribunal for claiming it. What you get depends on your own SPA, so read the delivery date and the compensation terms before you sign, not after.
I am an estate negotiator, not a lawyer. This page explains the usual system from published sources.
What LAD Is
Liquidated ascertained damages (LAD) is a pre-agreed amount of compensation written into the sale and purchase agreement. If the developer fails to deliver vacant possession within the time the contract allows, it owes you that compensation. Your SPA sets the amount and the period.
Where You Can Claim
The Tribunal for Homebuyer Claims. It is set up to resolve disputes between developers and buyers. The types of claim it commonly handles include late delivery of vacant possession, late delivery of common facilities, LAD, refund of deposit, refund of late interest, and defective workmanship or materials. One guide says that where there are no technical or legal complications, the Tribunal aims to give an award within 60 days of filing.
The courts. A law firm’s guide notes the Tribunal does not take away your right to sue in court, even for claims under the limit.
The Limit
The Tribunal can hear claims of up to RM50,000. If your claim is bigger, one option is to abandon the excess, and the Federal Court has confirmed that a buyer can bring separate, distinct claims for the same property, each within the RM50,000 limit. A law-firm article gives the example of an RM80,000 LAD claim being split. Because this is a legal tactic, get your lawyer’s view before relying on it.
The Check a Serviced-Residence Buyer Must Make
The Tribunal is described as covering a housing accommodation in Peninsular Malaysia. Many KLCC-area projects are serviced residences with a commercial title, so whether a particular unit counts is a question for your lawyer. Ask it before you pay, and look for the answer in the SPA, not the brochure.
Questions to Ask Before You Sign
- What is the delivery date in the SPA, and what is the LAD amount and rate?
- Does the Tribunal cover my unit’s title type?
- What does the SPA say about delays caused by events outside the developer’s control?
- Who do I contact, and in what form, to claim?
Related
- Is buying under construction safe for foreigners?
- Progressive payment schedule for a new launch
- How a foreigner buys a new launch, step by step
General information from published sources, not legal advice. Check the current rules and your own contract with a Malaysian lawyer.
Frequently Asked Questions
Sources & verification — Conventus Law — A practical guide to filing a claim at the Homebuyers Tribunal (RM50,000 cap, option to abandon the excess) (2026), Mah-Weng Kwai & Associates — Tribunal conditions: Peninsular Malaysia, housing accommodation, RM50,000, courts not excluded (2026), iProperty — Housing Tribunal: how to make a claim (types of claim, award timing) (2026), EdgeProp — Housing Tribunal may now award above RM50,000 for the same property but different issues (2026), Mondaq (MahWengKwai) — FAQ on liquidated damages for late delivery by developers (2020)
We cite official and primary sources wherever a claim can be checked. Rules and prices change — we re-verify everything at transaction time. Figures last verified: November 2026.
Ask me directly on WhatsApp
Send a message and I'll reply — usually within minutes. No form, no call-back queue.
WhatsApp me — send the unit, I'll run the numbers